1. The deliverables for BIM applications in schedule control should include the schedule management model, schedule warning reports, schedule plan change documents, and other related materials.
2. Beyond the common functionalities outlined in Article 3.0.6, BIM software dedicated to progress control should also provide the following specialized features:
1. Schedule adjustment capabilities;
2. Integration or attachment of actual progress data to the model;
3. Comparative analysis of progress across three different perspectives;
4. Progress warning notifications;
5. Approval processes for schedule changes.