General Regulations for BIM Use in Project Completion and Handover

BIM technology should be integrated throughout the construction project lifecycle, including during pre-acceptance, final acceptance, and final delivery phases.

2. The completion acceptance model must accurately reflect the actual conditions of the project. It should be developed based on the construction process model and include all relevant acceptance data and associated information.

3. All completion acceptance data linked to the acceptance model must comply with current standards, such as the Unified Standard for Construction Quality Acceptance of Building Engineering (GB50300) and the Management Regulations for Building Engineering Data (JGJ/T185).

4. The completion delivery model should be created based on the completion acceptance model, tailored to meet the specific requirements of the delivery objectives.

xuebim
Follow the latest BIM developments in the architecture industry, explore innovative building technologies, and discover cutting-edge industry insights.
← Scan with WeChat
Like(0) 打赏
BIM WORLD » General Regulations for BIM Use in Project Completion and Handover

Comment Get first!

Must log in before commenting!

 

BIM World, A Professional BIM Learning Platform

Stay updated on the latest architecture trends and share new building technologies.

Contact UsAbout Us

觉得文章有用就打赏一下小编吧

非常感谢你的打赏,我们将继续提供更多优质内容,让我们一起创建更加美好的网络世界!

支付宝扫一扫

微信扫一扫

Account Login

By signing in, you agree toUser Agreement

Sign Up