Configuring Standard Working Hours in Navisworks Projects

Setting Normal Working Hours in a Navisworks Project

Start by creating a new project. Notice that the horizontal timeline for Saturdays and Sundays is grayed out, indicating these are non-working days.

Next, we’ll create a 7-day task spanning from October 16th to October 24th—covering a total of 9 days, which includes 2 non-working days.

Right-click on the time scale and select Change Working Hours.

In the panel that appears, go to Work WeekDetailed Information. Here you can customize the working hours for each day of the week. For this example, modify the working hours for Saturday and Sunday by setting the start and end times to:

8:00–12:00 and 13:00–17:00

After making these changes, return to the timeline. You will see that the horizontal view is no longer grayed out; every day now appears as a working day.

Related Skills Search

How to Accurately Simulate Construction Time to the Hour in Navisworks

xuebim
Follow the latest BIM developments in the architecture industry, explore innovative building technologies, and discover cutting-edge industry insights.
← Scan with WeChat
Like(0) 打赏
BIM WORLD » Configuring Standard Working Hours in Navisworks Projects

Comment Get first!

Must log in before commenting!

 

BIM World, A Professional BIM Learning Platform

Stay updated on the latest architecture trends and share new building technologies.

Contact UsAbout Us

觉得文章有用就打赏一下小编吧

非常感谢你的打赏,我们将继续提供更多优质内容,让我们一起创建更加美好的网络世界!

支付宝扫一扫

微信扫一扫

Account Login

By signing in, you agree toUser Agreement

Sign Up