Step-by-Step Guide to Navisworks 4D Simulation

BIM Software Tip: Navisworks 4D Simulation Steps

1. First, adjust the view to clearly see the entire model.

2. Open the timeline module.

3. Navigate to the “Link” tab.

4. Right-click on the name and select “Add Link”. Then choose the appropriate document type.

5. Browse to the folder where your prepared construction details table is stored, and select the corresponding file.

6. In the field selector dialog box, map the timeline columns to the matching columns in the details table. Import the task type into the external field name, leave other fields as default, and click OK.

7. Right-click the new link in the name list and choose “Reconstruct Task Hierarchy through Link”.

8. Under the task, you will see all data from the detailed table, including the task’s start and end times. The task names will also correspond to the previously added search sets.

9. Return to the Rules tab.

10. Select the option to use the same name, map the timeline task from the name list to the selection set, and click Apply.

11. Go to the Simulation tab.

12. A timeline spanning the entire project duration will be displayed, allowing you to view the progress at any time. You can also play the simulation to watch the full process.

xuebim
Follow the latest BIM developments in the architecture industry, explore innovative building technologies, and discover cutting-edge industry insights.
← Scan with WeChat
Like(0) 打赏
BIM WORLD » Step-by-Step Guide to Navisworks 4D Simulation

Comment Get first!

Must log in before commenting!

 

BIM World, A Professional BIM Learning Platform

Stay updated on the latest architecture trends and share new building technologies.

Contact UsAbout Us

觉得文章有用就打赏一下小编吧

非常感谢你的打赏,我们将继续提供更多优质内容,让我们一起创建更加美好的网络世界!

支付宝扫一扫

微信扫一扫

Account Login

By signing in, you agree toUser Agreement

Sign Up